Skip to content

BLOG

SHARE

CruzAlta

Ops Constructability Review Delivers Exceptional Value by Eliminating Unnecessary Equipment and Streamlining Process Efficiencies

The Challenge

A major oil refiner in the U.S. was in the planning phase of a project to commission a new Naphtha Distillation Unit utilizing existing equipment in combination with adding new equipment. The existing workforce in this area in the refinery was well-versed in the normal operating duties of the area
but did not have the operations experience to successfully execute a major construction/commissioning project.

The Solution

CruzAlta provided a seasoned operations professional with a safety-focused culture, years of field-earned knowledge and practical operating philosophies to provide a streamlined focus and to highlight and correct
any deficiencies in the project.

We attended 3D model reviews at the engineering firm and identified items that would have impacted the project, such as operability interferences between piping and structural steel, as well as proper-sized drains to
accommodate faster shutdown/cleanup activities.

P&ID reviews identified several operability/control issues with the original design that required control valve relocation, instrumentation relocation or isolation issues that would have impacted the site’s ability to perform maintenance activities.

Identified cost-saving measures such as reviewing unit rundown temperature parameters to ensure downstream unit feed temperature is optimized to improve the efficiency of the unit receiving our product rundowns.

The Results

The identification of equipment not needed for the project has resulted in an estimated $3MM to $5MM savings in cost. The flip side of our participation is
we have identified items which have required further engineering refinement, resulting in a $2MM to $4MM expense from the engineering firm. The client is happy for the trade-off as the discovery during the engineering review resulted in a lower cost than having to re-engineer the issue during construction.

Identifying process efficiencies has resulted in a savings of $1MM annually. This is a conservative estimate as operating conditions and refinery fuel costs are very fluid. The ability to recover preheat in the downstream units
is difficult to quantify, but it is a definite savings in the unit fuel requirement for heat in the process furnaces.

 

 

LEAVE YOUR COMMENT